Metal Recovery and Slag Processing Co. - S.A.E. (SEPSCO) 2:

:

2-SLAG HANDLING :

-Removal of slag from under the Electric Arc Furnace (EAF) to the cooling area as often as required to allow the steel-making process to continue.

-Removal of slag from the Ladle Furnace area slag pen on a daily basis.

-Transportation of slag from the Electric Arc Furnace cooling area to the slag dump area by truck over a distance of not more than one kilometer from the plant.

-Transportation of the Ladle Furnace slag from the Ladle Furnace slag pen to the metal cutting area.

  

:

3-MATERIAL HANDLING:

-Raw Materials:These include Carbon, Lime, Coke, Ferroalloys etc.  These arrive to the plant in either containers or jumbo bags, which will be un-loaded and stored. Where the raw materials arrive in containers, they will be discharged from their containers before being transported to their storage area. These raw materials will then be transported to the belt conveyors as required.

-Refractories and consumables:Unloading of the incoming containers of Refractories (bricks/monolithic), Graphite Electrodes and any Spare Parts, discharging the materials from the containers and transporting the materials to their specified stores and reloading the containers on the trailers.