Metal Recovery and Slag Processing Co. - S.A.E. (SEPSCO) 3:
|
: |
4-DRI
& HBI HANDLING :
|
|
|
-Unloading,
piling and loading on trucks to be transported to conveyor
belts.
|
|
|
-Cleaning
the roads of falling D.R.I or
H.B.I
|
|
|
: |
5-SPARE
PARTS AND WASTE HANDLING:
|
|
|
|
-Includes
transporting of the Waste Refractories, all waste material in the
cooling chamber under the electric arc furnace, and also the waste
under the silos of the dust collection system, to the specified
waste area outside the plant.
This should be at a distance of not more than one kilometer
from the plant.
|
 |
|
: |
6-METAL
RECOVERY,TUNDISH & EMERGENCY SKULLS BREAKING:
|
|
|
-Loading
the tundish skulls and emergency skulls from the melt shop and
transferring them to the cutting and metal recovery area, where they
will be unloaded.
|
|
|
-Cutting
by oxygen lance or breaking by drop balling of:Tundish
Skulls, Emergency
Skulls and Ladle
Skulls.
|
|
 |